Critical Path Analysis: Techniques for Project Scheduling

  • from ITtoolkit.com

Image of a maze depicting a projects critical path.

What's on your critical path? Important tasks? Sure. Really important tasks? Of course. But is that all there is to it?  After all, every project task is important in some sense.  Within any project, the critical path is more than just a series of important tasks - it's a means for scheduling and management that relies on connections and consequences as a basis for planning project tasks and timelines.

As a project management technique, critical path analysis provides value in four (4) key respects:

  1. The critical path analysis is a means to estimate overall project duration.
  2. The critical path analysis is a basis to create a logical sequence of project tasks.
  3. The critical path analysis is a means to track project progress and identify delays.
  4. The critical path analysis is a basis to identify potential "fast-tracking" possibilities.

Practical Steps for Critical Path Creation

Critical path tasks are not considered "critical" on the basis of value or visibility, but on the basis of dependencies, which determine the overall length of the project. Since critical path tasks are connected tasks, a delay in one, can lead to a delay in all. As such, once identified, the critical path shows you what how to get your project done on time. 

Read more:  Project Scheduling Strategies

Critical path analysis relies on a few simple assumptions, as listed below:

  • Assumption #1 - Projects are made up of tasks.
  • Assumption #2 - Tasks are combined to form a timeline.
  • Assumption #3 - Within this timeline, tasks are either concurrent (can occur simultaneously) or sequential (one task cannot begin until the predecessor [superior task] is complete).
  • Assumption #4 - Sequential, dependent tasks make up the critical path.

Finding Your "Critical Path"

Critical path analysis begins with a task list, identifying all the key tasks required to complete the project at hand. This task list can be broken down into the following seven (7) key elements:

  • Tasks: Specific work activities.
  • Predecessors: Tasks that must be completed before any subsequent, dependent task can begin.
  • Durations: Task time estimates (from start to completion).
  • Early Start Time: The earliest point in the schedule at which a task can begin.
  • Early Finish Time: The earliest point in the schedule at which a task can finish.
  • Latest Start Time: The latest point in the schedule at which a task can start without causing a delay.
  • Latest Finish Time: The latest point in the schedule at which a task can finish without causing a delay.

From a practical standpoint, critical path analysis is all about creating "breathing room", to identify the tasks that must start and end at a specific point in time, versus those tasks which offer scheduling flexibility. Any worthwhile project management software will calculate critical path for you based on the tasks, dates and dependencies entered, but the logic behind these calculations should not be a total mystery, for it is the human element that must respond to project issues and changes on a daily basis - in real time.

Read more:  Project Management Checkpoints and Fundamentals of the Work Breakdown Structure.

Critical path analysis looks for the earliest and latest points at which tasks can begin and end. The calculation of earliest start times (EST) and earliest finish time (EFT) is used to create the project schedule. The calculation of latest start times (LST) and latest finish times (LFT) is used for schedule management, delay resolution, and fast-track planning.


Work Smarter

Even under the best of circumstances, management is a challenge. When you learn to fast track, you’ll learn to work smarter, not harder. And that’s the value of every lesson, resource and template available at Fast Track Manage Learning. We teach you how to fast track your way to successful projects, committees and more. Learn More


Calculations: Early Starts and Finishes

EST of tasks with no predecessors = First logical starting point.

EST of tasks with predecessors = Predecessor EFT (Earliest Finish Time).

EFT of tasks with no predecessors = Estimated task duration.

EFT of tasks with predecessors = (Task EST + Estimated task duration).

On the other side of the coin, latest start (LST) and latest finished times (LFT) are backwards calculations, considering the earliest starting point of the first subsequent task, minus the expected duration of the task under calculation. To calculate LST and LFT, you will start with the latest finish time and work backwards to calculate the latest possible start time.

Calculations: Late Starts and Finishes

Step 1 - Finding the LFT (latest finish time):

Considering the estimated "earliest start time" of any subsequent dependencies, what is the latest finish time for this task?

Task LFT = EST of the first dependent task.(Example: LFT of Task 1 = EST of Task 3)

Step 2 - Finding the LST (latest start time):

Considering the identified "latest finish time", what is the latest starting time for this task?

Task LST = (LFT – Task duration).

Example: LST of Task 1 = (Task 1 LFT - Task 1 Duration).

Source: Unless noted otherwise, all content is created by and for ITtoolkit.com


About Us

Right Track Logo

ITtoolkit.com staff writers have experience working for some of the largest corporations, in various positions including marketing, systems engineering, help desk support, web and application development, and IT management.

ITtoolkit.com is part of Right Track Associates, proprietors and publishers of multiple web sites including ITtoolkit.com, Fast Track Manage, HOA Board List and more. We started ITtoolkit.com in 2001 and have continued to grow our web site portfolio, Toolkit products, and related data services. To learn more, visit us at Right Track Associates.

Stay Informed

Useful information without inbox overload.

we do not sell our list

subscribe now
I.T. Service Planning The Fast Track Project Toolkit Start For Free

The IT Service Strategy Toolkit teaches you how to fast track IT service planning using the time-saving “service strategy process”. The goals are simple... to manage IT departments, services and projects in a common-sense manner, to align business and technology, and realize maximum value, acceptance, and utilization - all at the lowest overhead costs. It’s all about adding value, in less time and with greater success. Get lifetime access to a growing IT service curriculum of lessons, videos, reference materials, templates and more. Start for free.

Committee Management The Project Committee Toolkit Start For Free

The Project Committee Toolkit teaches you how to manage successful committees using the "committee concept" process. Committees are one of the most effective ways to organize, deliberate and make decisions. But too often, committee success is hampered by conflict and bureaucracy. When you follow the committee concept process, you’ll learn to avoid these pitfalls and ensure that your committees are properly formed, managed and staffed. Get lifetime access to a growing committee management curriculum of lessons, videos, reference materials, templates and more. Start for free.

Project Management The Fast Track Project Toolkit Start For Free

The Fast Track Project Toolkit teaches you how to deliver on-time, on-plan projects using "strategic project fast tracking". The fast track approach is a time-saving methodology, designed specifically for "real world" project circumstances - when you are being asked to do more than time and resources may allow. Fast tracking is the way to work around these obstacles and deliver prioritized results. Get lifetime access to a growing project planning curriculum of lessons, videos, reference materials, templates and more. Start for free.